Hi,

 I’ve had some blog responses back recently, but haven’t posted them because I’m not quite sure how! (It is not because they’re negative - although some are) I’ll try to arrange a tutorial with a colleague soon, and post them for you.

Checking my messages on the ‘phone, I note that the reason for the 13-months delay in improving the roadworks to junction 17 of the M60, is the following:

  • I asked for improvement work at the PLAP (then called Area Board) in January 2007
  • The Officer took this request & engineers investigated
  • In September 2007(!!!!), an order was placed to do the work
  • Because the juction is with a motorway roundabout, the slip roads need closing, and thus it has to be done through the Highways Agency, who get Contractors to do it on their behalf. The Contractors have not found a suitable date that works with the Highways Agency yet!
  • I’m now trying to get the Highways Agency to explain their delay!

I noted that a few calls from local papers had occurred recently, but because of work commitments, I was not able to respond in time for their deadlines.

Several planning & other personal issues have been dealt with for constituents, but confidentiality means I can’t put them on a blog!

Time for some real work now…